The contract encompassed a broad range of our in-house capabilities and underscored our integrated approach to project delivery.
Civmec’s scope included structural, mechanical, piping, electrical, instrumentation and communication (SMPEIC) works for the project, delivered successfully and on time in a condensed schedule.
The P1000 project was completed in a seven-month schedule that was delivered on time, allowing the client to produce and report first ore ahead of schedule. The SMPEI project involved the construction of a series of new or parallel unit processes which then tied into the existing flowsheet through a series of staged shutdowns and interface work.
The key goal of P1000 was to increase nameplate capacity of the Pilgangoora Operation from approximately 680,000 tonnes per annum (tpa) to 1 million tpa. At the project’s conclusion, we had installed 2,300 tonnes of steel, 1,100 kilometres of piping, and 145,000 metres of cable.